The €157,900 ceiling is what makes the unknown service work more important than the finish specification. This is a 105 m² small multifamily property in Utrecht, with renovation planned across the kitchen, bathrooms, surfaces and energy performance but no addition to the building.
Flooring and paint can be reduced or postponed if prices rise. Electrical replacement, moisture repairs and opening walls to reach plumbing are much harder to leave unresolved once work begins. I am therefore considering a general reserve for ordinary variation plus separate allowances for those concealed risks. Would that be more useful than one contingency percentage? I would also like contractors to identify exclusions, material lead times and who pays for making good after service access—for example, whether an electrical quote includes reopening and finishing the affected walls.
Flooring and paint can be reduced or postponed if prices rise. Electrical replacement, moisture repairs and opening walls to reach plumbing are much harder to leave unresolved once work begins. I am therefore considering a general reserve for ordinary variation plus separate allowances for those concealed risks. Would that be more useful than one contingency percentage? I would also like contractors to identify exclusions, material lead times and who pays for making good after service access—for example, whether an electrical quote includes reopening and finishing the affected walls.