The QAR 340,200 total looked comfortable until I started listing the work that could be hidden behind walls and floors. This is a preliminary budget for renovating a 70 m² detached home in Doha. The plan is to refit the kitchen and bathrooms, replace flooring, repaint, check the electrics and make modest efficiency improvements. There is no proposed structural enlargement.
What contingency would be sensible before any opening-up work? I want the surveyor and contractors to focus on plumbing access, moisture sources and the true electrical requirement rather than debating finishes.
I also need a clearer programme showing trade sequencing, permit assumptions and material lead times. Which evidence should I request before reducing the contingency: moisture readings, access inspections, an electrical assessment, written allowances, or firm supplier dates? Every exclusion and responsibility for making good would need to be stated as well.
What contingency would be sensible before any opening-up work? I want the surveyor and contractors to focus on plumbing access, moisture sources and the true electrical requirement rather than debating finishes.
I also need a clearer programme showing trade sequencing, permit assumptions and material lead times. Which evidence should I request before reducing the contingency: moisture readings, access inspections, an electrical assessment, written allowances, or firm supplier dates? Every exclusion and responsibility for making good would need to be stated as well.