I am torn between holding a generous contingency now and spending more first to expose the uncertain areas. The working budget is R$406,700 for a 35 m² mixed-use building in Rio, covering new kitchen and bathroom work, floors, decoration, electrical investigation and some energy improvements. No extension is intended, although I do not want to assume that means structural work is impossible.
The urgent temptation is to price everything and start ordering. A calmer route would be to investigate moisture, the condition and accessibility of plumbing and wiring, and any movement or structural concerns before fixing the scope. What should the surveyor open or test, and how should contractors itemise reinstatement, exclusions, lead times and permit dependencies when the access conditions are still uncertain?
The urgent temptation is to price everything and start ordering. A calmer route would be to investigate moisture, the condition and accessibility of plumbing and wiring, and any movement or structural concerns before fixing the scope. What should the surveyor open or test, and how should contractors itemise reinstatement, exclusions, lead times and permit dependencies when the access conditions are still uncertain?