The two quotations are too far apart to support a reliable contingency yet. They are meant to cover the same 200 m² Prague warehouse, within a preliminary CZK 9,955,000 budget, but I suspect the contractors have interpreted the brief differently.
The work includes staff kitchen and bathroom areas, new floor finishes, decoration, an electrical assessment and some energy improvements, without an extension. My concern is what each bid leaves out: remedial electrical work, opening up, waste removal, material lead times and coordination between trades.
Would you first normalise the bids into a common schedule, commission further investigation, or retain a larger reserve until the use and services are confirmed? Financing costs will be tracked outside the building-work allowance.
The work includes staff kitchen and bathroom areas, new floor finishes, decoration, an electrical assessment and some energy improvements, without an extension. My concern is what each bid leaves out: remedial electrical work, opening up, waste removal, material lead times and coordination between trades.
Would you first normalise the bids into a common schedule, commission further investigation, or retain a larger reserve until the use and services are confirmed? Financing costs will be tracked outside the building-work allowance.