Florida PMs: how do you pay vendors on bigger turn and repair jobs?

Florida property managers and owners: how do you handle vendor payments on bigger turn or repair jobs?On anything past a quick fix, say a roof section, a re-pipe or a full unit turn, do you pay on finished phases with photos, or a deposit and the balance at the end?

Do you ask for a Notice to Owner up front, or wait to see if one shows up? And do you collect lien releases from the contractor and suppliers before the final payment?

When the vendor is new to you, what's the minimum you verify before they start? License on MyFloridaLicense.com, insurance certificate, anything else?

I run a Florida home services marketplace, so the payment side of hiring is what I'm working on. I'd like to know what's actually holding up for PMs here, especially anyone who's dealt with a lien from a sub they never met.
 
Good question, Jason — and the lien-from-a-sub-you-never-met scenario is exactly why the paperwork matters as much as the work. I run a New Jersey turn crew, so Florida's Notice to Owner rules are not my home turf, but the process that keeps us out of trouble travels well.

On bigger turns and repairs we pay by finished phase, not by calendar date: each phase is photographed and signed off before the next payment is released, with a holdback until the final walkthrough. Before a new vendor starts, the minimum I verify is a current license, a certificate of insurance naming the owner or manager, and two recent references I actually call. A written scope with the phase list attached beats a handshake every time.

On the Notice to Owner and lien releases: get the notice question settled up front, in writing, before work starts — not when a lien shows up. And collect lien releases from the contractor and any known suppliers before the final payment, not after. The final payment is the only leverage you have, so do not give it up early.

What has held you up most — the verification, the phase sign-offs, or the releases at the end?
 
Good question, Jason — and the lien-from-a-sub-you-never-met scenario is exactly why the paperwork matters as much as the work. I run a New Jersey turn crew, so Florida's Notice to Owner rules are not my home turf, but the process that keeps us out of trouble travels well.

On bigger turns and repairs we pay by finished phase, not by calendar date: each phase is photographed and signed off before the next payment is released, with a holdback until the final walkthrough. Before a new vendor starts, the minimum I verify is a current license, a certificate of insurance naming the owner or manager, and two recent references I actually call. A written scope with the phase list attached beats a handshake every time.

On the Notice to Owner and lien releases: get the notice question settled up front, in writing, before work starts — not when a lien shows up. And collect lien releases from the contractor and any known suppliers before the final payment, not after. The final payment is the only leverage you have, so do not give it up early.

What has held you up most — the verification, the phase sign-offs, or the releases at the end?
Thanks, this is a great breakdown. Paying by finished phase with photos and a sign off before the next release is exactly how I like to see it done. For me the hardest part has been the releases at the end, mostly tracking down supplier releases on the bigger jobs. Collecting them before the final payment, while you still have that leverage, is the best advice in this thread. Appreciate you sharing how your crew handles it.
 
For a larger job, I’d lean toward clearly defined milestones, with any deposit tied to an explained upfront cost. “Bathroom complete” leaves plenty of room for disagreement. A written list of what must be installed, working and checked makes the payment decision much easier.

One distinction on the paperwork: a Notice to Owner generally comes from a subcontractor or supplier protecting their lien rights. It isn’t a clearance document. Florida’s guidance also recommends making responsibility for collecting lien releases explicit in the contract.
 
Jason, a running release register could put PropertyGuru's point about responsibility into practice: supplier or sub, contact, invoice or scope covered, payment stage, release requested and release received. Ask the contractor to keep it current during the job rather than assembling it at the final invoice.

Florida DBPR's construction-lien guide discusses partial releases for progress payments as well as final releases. A Florida construction lawyer can help you set the right documents and timing for your payment process. The register would track that process, not replace the legal checks.
 
Thanks, Jason — releases at the end are the hard part, and collecting them before the final payment, while you still have leverage, is the lesson I take from this too.

PropertyGuru and SecondViewing, the running release register is a practical idea: supplier or sub, what it covers, what stage, release requested and received, kept current during the job.

On the Florida lien paperwork itself, I am in New Jersey, so I will not give Florida legal advice here — that is for a Florida construction lawyer. The process point I can share is the one above: milestones in writing, photos and sign-off before each payment, and releases collected before the last payment.
 