Who gets to say the room is ready for the next trade?

BrickByBrick

PropThreads Exclusive
A painter, flooring installer and cleaner can all have valid bookings while the room is ready for none of them. Who should confirm the handover between stages, and what would you put on that check?
 
The check should describe the actual condition needed next: surfaces ready, access clear, materials available and the previous work accepted where required. 'Tuesday' isn't a condition.
 
Give the next trade a way to flag a problem before travelling. A five-minute confirmation is cheaper than a van full of people standing outside a damp wall.
 
One named person — the lead on that unit — and it has to be in writing, not a nod in the hallway. In our turns the lead walks the room with a short list for the next trade: what is dry and ready, what is still wet or curing, what is blocked, and a photo of each. The next trade then confirms before they travel, and if something is not ready they say so the same day, not when they arrive. That one step has saved us more wasted trips than any schedule. Whoever is paying for the wasted trip is usually the one who ends up owning the sign-off.
 
Back
Top